It takes 14 electricians 18 days to wire a new housing subdivision. How many days would it take 24 electricians to do the same job?

Respuesta :

imlittlestar
imlittlestar imlittlestar
  • 11-11-2018

Answer = 21/2 days or 10 and 1/2 days

It takes 14 electricians 18 days to wire a new housing subdivision.  

One  electrician take more time to wire a new housing subdivision.

So one electrician take 14 x 18 days to complete the job.

Therefore 24 electricians take  less time to complete the job.

Number of days taken by 24 electricians to wire a new housing subdivision.= (14 x 18 )/24=21/2 days


Therefor 24 electricians take (14 x 18 )/24=21/2 days



Answer Link
AnswersForYou
AnswersForYou AnswersForYou
  • 15-10-2019

Answer:

10.5 days

Step-by-step explanation:

Answer Link

Otras preguntas

The study of the human body A. Anatomy B. Botany C. Physiology D. Psychology
how many times does 20 go into 190
Mandy is creating an outline for her research paper. What does she need to include in the outline?
what are some reasons that humans need to be concerned with our environment? explain.
0.8+0.8=0.6k+0.9 What is k?
English help please!!
A definition of formal poetry is verse that A. uses figurative language. B. is written in blank verse. C. has no rhyme scheme. D. sticks to certain traditional
Identify the subordinate clause. The book that I am reading concerns world population problems. the book the book that I am reading book that I am reading that
What is the value of a in the equation 3a + b = 54, when b = 9?
Hypertension is NOT a type of cardiovascular disease. a. True b. False