brimccauley6658 brimccauley6658
  • 03-08-2022
  • Business
contestada

In a project network, the critical path is the sequence of activities which has the:________.

Respuesta :

66hello60
66hello60 66hello60
  • 03-08-2022

Answer:

The correct answer is the longest time

Answer Link

Otras preguntas

Find the explicit formula that produces the given sequence. 3/2, 3/4, 3/8, 3/16,...
What Is Geographic Mobility?
What are the essential 4 parts for a civilization to develop? Explain how rivers were the source of civilization?
how many variables should you have in a control experiment?
What is the next number of the pattern. 2 7 26 101 400
Hello how do you solve for x a= x-b/y
What does it mean when Brutus says: "Into what dangers would you lead me, Cassius... that you would have me seek into myself...for that which is not in me?
one way in whick Robespierre and Louis XVI of France are similar is that both
Solve for x/4-x+2/6=x/3
how do I divide a fraction to a decimal