It takes 12 men 5 days to complete a job. Work out how many days it would take 3 men to complete the same job.

Respuesta :

Esther
Esther Esther
  • 03-03-2022

Answer:

20 days

Step-by-step explanation:

It takes 12 men 5 days to complete a job. Work out how many days it would take 3 men to complete the same job.

12 * 5 = 60

60/3 = 20

It will take 3 men 20 days to do the same job

Answer Link

Otras preguntas

PLease help!!!:):) The light in this diagram is producing light. Which best describes the process of energy conversion to accomplish this? A. The magnetic ener
Why Is Diffusion Important To Plants And Animals?
The Jayden family eats at a restaurant that is having a 15% discount promotion. Their meal costs $78.96, and and they leave a 20% tip. If the tip applies to the
HELPPPPP MEEEEEEEEE.
A sample of Ca(OH)2 is considered to be an Arrhenius base because it dissolves in water to yield A. Ca2+ ions as the only positive ions in solution B. H3O+ ions
What is the purpose of archaebacteria?
What is Cyrus's enduring legacy?
What Are The Branches Of Botany?
Why do we only see only one side of the moon from Earth A. the moon does not rotate B. the moon takes longer to rotate then to revolve around Earth C. the moon
Which hydrocarbon is saturated? (1) propene (3) butene(2) ethyne (4) heptane