It takes 12 men 5 days to complete a job. Work out how many days it would take 3 men to complete the same job.

Respuesta :

Esther
Esther Esther
  • 03-03-2022

Answer:

20 days

Step-by-step explanation:

It takes 12 men 5 days to complete a job. Work out how many days it would take 3 men to complete the same job.

12 * 5 = 60

60/3 = 20

It will take 3 men 20 days to do the same job

Answer Link

Otras preguntas

According to postman what is the danger of depending on tv as a myth
A dog runs out of the back door of a house and stops to grab a bone. Then the dog returned to the house. Graph shows the motion of the dog. For how many seconds
How does Buck change from the beginning of the story to the end? From Call of The Wild
Six consecutive numbers starting from 33 are multiplied. Which of these digits will be in the ONES' place in the resulting number?
I NEED HELP ASAP PLEASEEEE.A roller coaster ride starts with the roller coaster car being pulled to the top of the first hill with a pulley system. The car is r
hello help me please presentar el programa : introduccion el ritmo y su transmision en el mundo. que es el ritmo bolero ? su creacione musicale, su evolucion y
find the unit rate: 297 words in 5.5 minutes
A 5 year-old patient is experiencing atrial fibrillation with rapid ventricular rate. the anesthesia department is called to insert a nontunneled central venous
2.5 moles of sodium chloride is dissolved to make 0.050 liters of solution
For triangle MNP with vertices M (-4, -2), N (6, -2), and P -2, 10). Find the coordinates of each one. the centroid the orthocenter