Three workers can do a job in 28 hours. How many more workers are needed to do this job in 12 hours?

Respuesta :

MrRamon
MrRamon MrRamon
  • 13-04-2018
4 additional workers for 7 total workers.
if it takes 3 workers 28 hours to do work there are 84 total hours of work (3*28=84) to find how many workers it will take to get the work done in 12 hours divide 84 by 12. 84/12= 7 total workers. 7-3= 4 additional workers needed.
Answer Link
pranilraichura
pranilraichura pranilraichura
  • 08-03-2020

Answer:

4 workers

Step-by-step explanation:

Answer Link

Otras preguntas

A square has a side length equal to 6a-2b inches. What is the area of this square
Every population is part of a ___? Help plz!! I'll mark brainliest!
SOMEONE HELP reporting for stupid answers
Why do you think the author chose to include the conversation between Mr. Malloy and his boss and the conversation between Philip's parents. NBTT HELPPPP
Where might you see a ball game while visiting a new city? el parque de diversiones el hotel el árbol el estadio
Find the slope of the line containing the pair of points. (-1,3) and (7,0)?
Explain four suggestions for treating anxiety as mentioned in the article
Identify the domain and range. Set up a table of values. f(x)=square root of x+1​
Fix the one word that is used incorrectly. You should poor cold water over pasta once it's done to stop it from overcooking.
Fill in the table below of the Interactive Word Wall. You are provided with thecommon online activities, fill in the competencies/ skills that would fall under