Three workers can do a job in 28 hours. How many more workers are needed to do this job in 12 hours?

Respuesta :

MrRamon
MrRamon MrRamon
  • 13-04-2018
4 additional workers for 7 total workers.
if it takes 3 workers 28 hours to do work there are 84 total hours of work (3*28=84) to find how many workers it will take to get the work done in 12 hours divide 84 by 12. 84/12= 7 total workers. 7-3= 4 additional workers needed.
Answer Link
pranilraichura
pranilraichura pranilraichura
  • 08-03-2020

Answer:

4 workers

Step-by-step explanation:

Answer Link

Otras preguntas

If the velocity of a proton is straight up (thumb pointing up) then RHR2 shows that the force points to the left. What would the direction of the force be if th
which process must occur for clouds to form?
Clear parentheses and combine like terms:​
Which of the following are correct descriptions of large corporations? a) Managers no langer have the incentive to act in their own interests. b) The corporatio
Which statement is most likely to be true about a computer network? a. A network can have several servers and only none client. b. A network has to have physica
its my birthday boys, and girls
What elements of the world and human nature does this creation myth explain? Cite text evidence in your response.
If skin cancers is related to UV light that people with high exposed to UV light we have higher chance of getting skin cancer what is the In dependable Independ
If 10 chips are 130 cals how much is just one chip?
Which layer of the atmosphere leads to space?