32 workers can complete a work in 30 days working 6 hours per day. How many days are required to complete the
same work by 16 workers working 8 hours per day?

Respuesta :

mhanifa
mhanifa mhanifa
  • 03-09-2021

Answer:

  • 45 days

Step-by-step explanation:

Total man hours:

  • 32*30*6 = 5760

Required days:

  • 5760/(16*8) = 45
Answer Link

Otras preguntas

A patient has a blood sugar of 49mg/dl documented in the record. Which of the following would you most likely see listed by the physician as a diagnosis for t
What are the solutions of the system? Solve by graphing. y = -x^2 -6x - 7 y = 2
I need help with all of them thanks!(19 points)
(This is just for fun) "Alexander Hamilton had a torrid affair and he..."(Hamilton reference) :)
You are at a restaurant and owe $38 for your meal. You want to leave a 20% tip. How much will your tip be?
Which of the following sex and generation combinations directly produces the pollen tube of angiosperms?A) male gametophyteB) female gametophyteC) male sporophy
Which expression is equivalent to 3^3 + 2^2?
The distance between two cities is 368 miles. If the scale on the map is 1/4 inch=23 miles, what is the distance between the cities on the map?
Need help ASAP please
when did the spanish war start