Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

Can someone use the word delta in a sentence
what is the answer for (20,8),(9,16) ?
Data are drawn from a symmetric and bell shaped distribution with a mean of 120 and a standard deviation of 5. There are 900 observations in the data set. What
Find Domain of the functionsquare root of (x-8)/x(x-9)
how is mass transit in cities a possible solution tk urban air pollution?
what is the answer for (20,8),(9,16) ?
Data are drawn from a symmetric and bell shaped distribution with a mean of 120 and a standard deviation of 5. There are 900 observations in the data set. What
Can someone use the word delta in a sentence
Historians of china have traditionally dated the beginning of Chinese civilization to the founding of the what??
How were life forms affected by the rise in atmospheric oxygen levels that began 2.2 billion years ago?